sibutramine diet pills

Currently sometimes a little busy with other stuff

8 months 3 weeks ago 8 months 3 weeks ago by -SD-DELTON-ACI-.
-SD-Sundude
-SD-Member
-SD-Member
Posts: 12
More
Topic Author
Currently sometimes a little busy with other stuff #493
Might not be playing just as much this summer...




The following user(s) said Thank You -SD-Peacefulfury, -SD-Dorr, -SD-TeRRoRz

Please Log in or Create an account to join the conversation.

8 months 3 weeks ago 8 months 3 weeks ago by -SD-Peacefulfury.
-SD-Peacefulfury's Avatar
-SD-Peacefulfury
Senior admin
Senior admin
Posts: 230
More
Currently sometimes a little busy with other stuff #494
Is this an upgrade or a repair?

Well whichever it is good luck with it :)

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-Bossie's Avatar
-SD-Bossie
Senior Admin BG Staff
Senior Admin BG Staff
Posts: 276
More
Currently sometimes a little busy with other stuff #495
Looks like a lot of work. Goodluck :)

Slim & Fit

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
jimmyboy1952's Avatar
jimmyboy1952
VIP Member
VIP Member
Posts: 192
More
Currently sometimes a little busy with other stuff #496
WOW hope you are not on that job on your own ...... good luck

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago 8 months 2 weeks ago by -SD-Sundude.
-SD-Sundude
-SD-Member
-SD-Member
Posts: 12
More
Topic Author
Currently sometimes a little busy with other stuff #497
Full renovation of the basement, But there was issues with the bathroom upstairs (water leaking though the floor). When the plumber removed the concrete to install a new drain. he was not gentle and made a crack in the floor concrete, so we had to repaired it during moveing to toilet to another placement.

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-Silicon's Avatar
-SD-Silicon
-SD-Member/Donator
-SD-Member/Donator
Posts: 108
More
Currently sometimes a little busy with other stuff #498
Held og lykke og god arbejdslyst ;)

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-THEBOGEYMAN's Avatar
-SD-THEBOGEYMAN
-SD-Member
-SD-Member
Posts: 180
More
Currently sometimes a little busy with other stuff #499
I would just use some SILICON sealer,, Job done

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-CrashO's Avatar
-SD-CrashO
-SD-Member
-SD-Member
Posts: 127
More
Currently sometimes a little busy with other stuff #500

-SD-Silicon wrote: Held og lykke og god arbejdslyst ;)

Far, vi modtager den underlige radiostation igen :whistle:

There was a idiot with a pc,
and CrashO was his name-o.

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-Sundude
-SD-Member
-SD-Member
Posts: 12
More
Topic Author
Currently sometimes a little busy with other stuff #501
Tak, næste gang så tager vi en snak på dansk ;-)

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-MxJames's Avatar
-SD-MxJames
-SD-Member/Donator
-SD-Member/Donator
Posts: 536
More
Currently sometimes a little busy with other stuff #503
Did you drill that rebar into the current concrete with resin?? looks like its just laying on the insulation ? !?

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-Sundude
-SD-Member
-SD-Member
Posts: 12
More
Topic Author
Currently sometimes a little busy with other stuff #515
The insulation is to stop the concrete from filling the basement, :-)
Its cheap and works fine when supported by supporting pilers (do not know the English term, but in Danish they are called soldiers, as they stand up straight). One could also use Shuttering Plywood, but for this type of work insulation of a sufficient thickness is fine).
Rebar are drilled into the existing floor concrete and the hole filled with anchoring Mass to remove air and fix the rebar (avoid rust). Rebar are a few centimetres from the insulation (min 3cm) . both top and bottom, so concrete will get a strong bond with the rebar. same as laying a new concrete floor.

Please Log in or Create an account to join the conversation.

8 months 2 weeks ago
-SD-MxJames's Avatar
-SD-MxJames
-SD-Member/Donator
-SD-Member/Donator
Posts: 536
More
Currently sometimes a little busy with other stuff #516
Perfect :) yea i know the insulation was shuttering, its quite strong stuff considering the weight of it. We call the soldiers acrow.

I was just worried the rebar looked like it was touching the insulation and not fixed into previous concrete, so the concrete would only be supported but its grip on previous

concrete edge. a Dangerous weight to fall ;) but no you done it properly :D

Please Log in or Create an account to join the conversation.

5 months 1 day ago 5 months 1 day ago by -SD-DELTON-ACI-.
-SD-Sundude
-SD-Member
-SD-Member
Posts: 12
More
Topic Author
Currently sometimes a little busy with other stuff #1543
Work and work..
Removed windows and made new window hole
Electricity pipes and outlet build into walls
Removed heating , temporary water heater
New water heater, new pipes, new room heater unit, for the floor heating pipes.
New water (cold and hot) almost done
House heating done tomorrow
New windows and new door in about +2 months :-(
Still missing to dig for installing of wall isolation at the front road and new roof water well to sewer digging , maybe next weekend... or spring next year

Also time for wine and pool :)









Please Log in or Create an account to join the conversation.

5 months 1 day ago
-SD-MxJames's Avatar
-SD-MxJames
-SD-Member/Donator
-SD-Member/Donator
Posts: 536
More
Currently sometimes a little busy with other stuff #1545
looking good, why 6 and a half loops on the manifold? or are my eyes bleary

Please Log in or Create an account to join the conversation.

5 months 1 day ago
-SD-MxJames's Avatar
-SD-MxJames
-SD-Member/Donator
-SD-Member/Donator
Posts: 536
More
Currently sometimes a little busy with other stuff #1546
nm u got 3 zone pipes gues one on manifold is spare. I like the levels of your copper pipes. nice and straight ;)

Please Log in or Create an account to join the conversation.

5 months 1 day ago
-SD-Sundude
-SD-Member
-SD-Member
Posts: 12
More
Topic Author
Currently sometimes a little busy with other stuff #1547
There is one spare water each in each manifold (cold/warm), for a work/small kitchen sink in the basement. The manifold can be extended if required.

The copper pipes and the alupex pipes was done by a Plummer, and many are not all straight(the picture angel hides it a bit), so they will have to redo/correct it. We gave up on the Plummer on the bottom manifolds and did it ourself and used our own manifolds that had the correct spacing (in the picture). Not that impressed with the plummer work. also the water heater manual states that optimally it should be a lest 20cm from the ceiling. it is only 12 cm. They will come and do the house heating pipes today and back again later to correct the not straight pipes - both copper and alupex (without charging).
Still alot of work.. but for a while much of it will not be me doing the work.

Please Log in or Create an account to join the conversation.

5 months 14 hours ago 5 months 14 hours ago by -SD-MxJames.
-SD-MxJames's Avatar
-SD-MxJames
-SD-Member/Donator
-SD-Member/Donator
Posts: 536
More
Currently sometimes a little busy with other stuff #1550
My last, had no room lol
Attachments:

Please Log in or Create an account to join the conversation.

5 months 13 hours ago
-SD-Sundude
-SD-Member
-SD-Member
Posts: 12
More
Topic Author
Currently sometimes a little busy with other stuff #1552
AMG, alot of pipeing with no room, but looks quite straight and all copper :-). No isolation? Did you do it yourself or?
Do you have a very big house..

Please Log in or Create an account to join the conversation.